ISTS Waiver

To promote the development of renewables in RE-rich states and encourage inter-state procurement of renewables, the central government allowed waiver of ISTS charges and losses for solar and wind projects in 2016. Through various subsequent orders, the Ministry of Power (MoP) extended the deadline of ISTS waiver for some solar and wind project categories commissioned till 30th June, 2025. Recently, the ambit of the waiver has been widened for green hydrogen, large hydro plants, pumped storage hydro (PSH) and battery storage (BESS). We have tracked the several amendments and evolution of the ISTS waiver framework since 2016 below.

MoP Order Nov 2019

Download Principal Document  
Date of Notification
6th November, 2019
Wind
Amendment in Feb 2018 order
1. No ISTS charges and losses will be levied on transmission of electricity through ISTS system for sale of power by such projects commissioned till 31st December, 2022.
Solar
Amendment in Feb 2018 order
1. No ISTS charges and losses will be levied on transmission of electricity through ISTS system for sale of power by such projects commissioned till 31st December, 2022.