Tariff Regulations
Maharashtra
The Maharashtra Electricity Regulatory Commission has issued the Multi Year Tariff regulations dated 1st August 2019. The regulation is effective from April 1, 2020 to March 31, 2025. The primary purpose of the regulations is to determine of Aggregate Revenue Requirement, Tariff, and Fees and Charges of generating companies, transmission & distribution licensees and SLDC.
MERC MYT Regulations 2019
[clause 1.3]
[clause 2.23]
[clause 2.25c]
Gas Insulated Substation (GIS) – 35 years
Transmission line (including HVAC & HVDC) - 35 years
[clause 2.89]
b. Variation in amount of interest on working capital
c. Variation in Operation & Maintenance expenses
[clause 9.2]
b. Change in law
c. Variation in inter-State Transmission Charges
d. Variation in market interest rates for long term loans
[clause 9.1]
2. The balance amount, which will amount to two-thirds of such gain, may be utilised at the discretion of the Transmission Licensee
3. One-third of the amount of such loss may be passed on as an additional charge in tariffs over such period as may be stipulated in the Order of the Commission
4. The balance amount of loss, which will amount to two-thirds of such loss, shall be absorbed by the Transmission Licensee
[clause 11]
1.1. For full recovery of Annual Transmission Charges:
(i) AC system: 98%
(ii) HVDC bi-pole links and HVDC back-to-back stations : 95 per cent
1.2. For Additional Rate of Return on Equity consideration:
(i) AC system : 99 per cent;
(ii) HVDC bi-pole links and HVDC back-to-back stations : 96 per cent;
2. Recovery of annual transmission charges below the level of target availability shall be on pro-rata basis, and at zero availability, no transmission charges shall be payable.
3. For AC system, two trippings per element per year shall be allowed,
4. In case of outage of a transmission element affecting evacuation of power from a generating Station, outage hours shall be multiplied by a factor of 2
.[clause 60.1]
(a) O&M expense per ckt-km
- 765 kV : Rs. .86 lakh per ckt-km
- 400 kV : Rs. 0.61 lakh per ckt-km
- >66kV&66kV&
(a) Transmission system access charges
(b) Annual transmission charges
(c) per unit charges for energy transmitted
(d)Reactive energy charges
[Clause 57.1]
2. The Annual Transmission Charge payable by Transmission System User shall be computed in accordance with the following formula:
2.1. ATC(u)(t) = TTSC(t) X ([Base TCR(u)](t) / Σ u=1 to n [Base TCR(u)](t))
Where,
ATC(u)(t) = Annual Transmission Charges to be shared by Transmission System User (u) for the yearly period (t)
Base TCR (u) = [CPD(u)(t) + NCPD(u)(t)] /2
Where,
Base TCR represents the Base Transmission Capacity Right of each Transmission System User (u) for the yearly period (t)
CPD (u)(t) = Average Coincident Peak Demand of the Transmission System User (u) for the yearly period (t)
NCPD (u)(t) = Average Non-coincident Peak Demand of the Transmission System User (u) for the yearly period (t)
[clause 65]
2. The quantum of energy consumed by the auxiliary equipment of a transmission sub-station and the station transformer losses within the sub-station shall not be accounted for under the Transmission Losses
3. Provided further that the energy consumed for supply of power by the transmission sub-station to the associated offices of the Licensee, its housing colony and other facilities, and for construction works at the sub-station, shall not be considered as energy consumed by the auxiliary equipment of a transmission sub-station.
[clause 69]
[clause 36]
2. Reactive energy exchange, only if made as per the directions of MSLDC, for the applicable duration (injection or absorption) shall be compensated/levied by the MSLDC to the Generating Station, as specified in the MERC (State Grid Code) Regulations, 2006.
3. The Transmission System Users shall be subjected to Incentive/Disincentive to be compensated/levied by the MSLDC for maintaining the reactive energy balance in the transmission system, as specified in the MERC (State Grid Code) Regulations, 2006.
[clause 70]